Energie « Terug naar discussie overzicht

Kernenergie

847 Posts, Pagina: « 1 2 3 4 5 6 ... 19 20 21 22 23 24 25 26 27 28 29 ... 39 40 41 42 43 » | Laatste
voda
0
China installs steam generator at Tianwan unit 6

World Nuclear News reported that the second of three steam generators at China's forthcoming Tianwan 6 nuclear power unit has been installed, completing a 12-day process that involved bringing the component through a hatch and rotating to a vertical position. The achievement on 8 April was announced today by China Nuclear Industry 23rd Construction Company. Units 5 and 6 at Tianwan are domestic design ACPR1000 pressurised water reactors that will produce 1080 MWe when commissioned.

The first four units at the site are Gidropress VVER units supplied by Russia, as will be the seventh and eighth, for which a general contract was signed last month. When they are all in operation Tianwan would become the largest nuclear power plant in the world with eight units and a total generating capacity of about 8100 MWe.

Source : World Nuclear News
voda
0
Russia puts first concrete for second Kursk II unit

World Nuclear News reported that main construction work for the second unit at Kursk II in Russia has begun two weeks ahead of schedule. The site in Western Russia is the first to use the VVER-TOI (typical optimised, with enhanced information) reactor design. Rosenergoatom Director General Andrei Petrov said that Pouring of the first cubic metre of concrete into what will become the base plate of unit 2's reactor building is a "considerable milestone" for the project. He talked about series construction of the reactors: "Last April the first concrete of the nuclear basemat of unit number 1 at Kursk II was poured. And now we start main construction works at unit number 2 ahead of schedule."

The 1255 MWe VVER-TOI - described by Petrov as Russia's "most advanced" modern nuclear reactor - is a Generation III+ power unit and was developed using technical results from the VVER-1200 project. The design offers improved safety measures, including an increased margin of safety from extreme impacts and ability to withstand earthquakes, and is equipped with modern control systems and diagnostics, Rosatom said.

Kursk II will also be the first Russian nuclear power plant to have a digital automated system for managing costs and scheduling during the construction process. Construction timeframe, costs and operational costs are expected to show a "significant reduction" for the VVER-TOI in comparison to Generation III+ units such as Novovoronezh II units 1 and 2 and Leningrad II units 1 and 2, Rosatom said.

First concrete for Kursk II unit 1 was poured in April 2018, and Rosatom on 10 April announced completion of the installation of the first section of the unit's inner containment. The installation of the 15 metre x 9 metre reinforced blocks making up the structure - each weighing 50 tonnes - took almost a month. The blocks must now be joined into a single construction, before concrete is poured into the annular walls to a depth of 4 metres.

Source : World Nuclear News
Bijlage:
voda
0
Russia & Ethiopia sign road map on joint nuclear projects - Rosatom

UrduPoint News reported that Russia and Ethiopia signed a three year road map on cooperation in constructing a Center for Nuclear Science and Technology and a nuclear power plant in the African state. Russian State Atomic Energy Corporation Rosatom said that the document was signed within the framework of the 11th Atomexpo international forum, which is currently ongoing in Russia. The Russian side was represented by Rosatom CEO Alexey Likhachev, while Getahun Mecuria, the Ethiopian minister of innovation and technology, signed the document on behalf of Ethiopia.

Rosatom said in its statement that "The roadmap determines specific steps in strengthening bilateral cooperation in the field of peaceful use of atomic energy. The parties plan have identified joint actions within the framework of NPP construction and CNST construction projects. Thus, a foundation is laid for training personnel and raising public awareness about atomic energy.”

On June 19, 2017, Rosatom and the Ethiopian Ministry of Innovation and Technology signed a memorandum of understanding on cooperation in the peaceful use of nuclear energy. The memorandum provided a legal basis for bilateral cooperation in such areas as the development of nuclear infrastructure and raising public awareness of nuclear technologies and it use.

The Atomexpo 2019 annual forum, organized by Rosatom, opened in the Russian resort city of Sochi earlier on Monday and will last through Tuesday. The 11th edition of the conference has brought together over 1,500 foreign participants from 74 countries.
Image
Source : UrduPoint
voda
0
Construction of Egypt’s first nuclear power plant to begin in 2020

Egyptian Nuclear Regulation and Radiological Authority has granted the Nuclear Power Plants Authority site approval permit for the construction of Egypt’s first nuclear power plant. The construction of El Dabaa nuclear power plant is planned to take place 250km west of Alexandria city in Matrouh Governorate on the Mediterranean coast, and is expected to begin in 2020, with commissioning expected in 2026. The proposed plant will be developed by Russian State Atomic Energy Corporation ROSATOM under the ownership of the Nuclear Power Plant Authority of Arab Republic of Egypt, which will also operate it.

In 2015, the Ministry of Electricity and Renewable Energy of Egypt signed an agreement with Russian state-owned company ROSATOM to build, finance and operate the nuclear plant, and notices to implement the previously signed contract were signed on December 2017.

According to Rosatom, the plant will consist of four Russian-designed VVER-1200 pressurized water reactors, which are capable of producing 1.2GW each. The first unit is expected to begin commercial operations in 2026, while commissioning of the remaining three reactors is scheduled for 2028.

The VVER-1200 reactor is a third-generation pressurised water reactor that is fully compliant with all international safety and post-Fukushima IAEA requirements. It is designed to withstand the crash of a 400t airplane or earthquakes up to an intensity of 9 on the Richter scale.

Other than low regional seismic activity and sufficient cooling water supply, the proposed site is in close proximity to necessary infrastructure including rail, road and power transmission interconnections.

A financing agreement signed between the Finance ministries of Egypt and the Russian Federation indicates that Russia will fund approximately 85% of the construction cost of the project through a US$25bn loan granted to Egypt, while the remaining 15% will be raised by Egypt from private investors. The loan is repayable over a period of 22 years at an interest rate of 3% a year.

Source : Strategic Research Institute
voda
0
Belarusian nuclear power plant to cost less - President

BelTA reported that the cost of building the Belarusian nuclear power plant will be lower than the previously mentioned sum of USD 10 billion. Belarus President Aleksandr Lukashenko made the relevant statement as he answered questions from parliamentarians.Aleksandr Lukashenko said that the problem had been discussed at one of his meetings with President of Russia Vladimir Putin. The Belarusian head of state drew attention of his Russian counterpart to the fact that the Belarusian-Russian credit agreement provides for lending up to USD10 billion while the real price will be less than USD 7 billion. He said “The cost of the nuclear power plant will be lower. We will see it once all things are done. But I've mentioned this figure to Vladimir Putin once.”

The head of state added that the Belarusian nuclear power plant will also be cheaper because spending is closely overseen.

Source : BelTA
voda
0
Holtec to acquire Indian Point nuclear plants in New York

Holtec International subsidiary has agreed to acquire and decommission a nuclear-power complex on the Hudson River north of New York City. Holtec, which sees a business opportunity in scrapping outdated nuclear plants, announced an agreement to acquire the Indian Point complex from Entergy Corp.

Holtec also said its previously announced plans to acquire nuclear generating stations in South Jersey and Massachusetts are moving smoothly through the (US Nuclear Regulatory Commission’s) system.

The Camden firm predicted a license transfer for Oyster Creek, an Ocean County facility that stopped producing power last year, could occur by July 1. It has said the plant’s decommissioning could take eight years.

A license for the Pilgrim plant on Cape Cod could be transferred six weeks later, it said.

Source : Strategic Research Institute
Bijlage:
voda
0
Fennovoima to start constructing nuclear plant with Russian reactor in 2021 in Finland

New Europe reported that Fennovoima is proceeding with plans to build the Hanhikivi 1 nuclear power plant in the northern Finnish city of Pyhäjoki and expects to receive the construction license in 2021 as against original plans in 2019. Fennovoima CEO Toni Hemminki told New Europe “At the end of the year, the supplier, RAOS Project, communicated to us that, according to the estimation, we can start the construction in 2021 and then that means commercial operational date would be the 2028. Those are the milestones that we are working on accordingly at the moment and we are also fine tuning the detailed schedule for it with the supplier.The structure with the supplier is the same but there have been some organizational changes within Fennovoima. We have realized that we need or we wanted to raise the bar of the organization so we can support the supplier better to fulfill the Finnish requirements.”

He reminded that the plant would have power of 1200 MW, using a Russian VVER-1200 reactor.

He added “The license phase is planned to be finished in 2021. Basically when you get the construction license, then you can start to build nuclear-related buildings and you can start to manufacture nuclear-related equipment. So we plan to get the construction license in 2021 and then start the construction immediately.”

Source : New Europe
voda
0
12 more nuclear power plants in India soon - Department of Atomic Energy chief

Economic Times quoted Secretary of the Department of Atomic Energy, Mr KN Vyas as saying that India will soon have 12 more nuclear plants soon to improve the power situation and ensure there is a free flow of uninterrupted power supply for both industries and residential use. Mr Vyas said that "Nuclear technology helps in betterment of lives through varied usages and is an irreplaceable source of clean, pollution-free energy.” He said the founder of Indian nuclear programme, Homi J. Bhabha, had envisaged that nuclear technology is going to be "very essential" and not just in the power sector but for other societal uses intended for betterment of life.

Mr Vyas further said that "We believe that when it comes to clean energy, there is no substitute to nuclear energy as it is sustainable and without interruption, one can have clean energy.”

Citing the record run of Kaiga Nuclear Power Station, he said a small unit of indigenously-developed 220-250MW reaction has completed 962 days of uninterrupted run at about 99.3 per cent capacity and the amount of electricity it has generated is "tremendous".

Mr Vyas said the first stage of India's indigenous nuclear power programme has now attained maturity with 18 operating Pressurised Heavy Water Reactors (PHWRs).

Source : Economic Times
voda
0
Russia expects operating licence for floating nuclear power plant in July

World Nuclear News reported that after a series of successful and comprehensive tests, including on its twin KLT-40 reactor system, the floating nuclear power plant Akademik Lomonosov is ready to start commercial operations. Russia's Rosatom said that the plant's two reactors were successfully brought up to 100% capacity on 31 March. These tests confirmed the operational stability of the main and auxiliary equipment of the plant, as well as the automatic process control systems.

Mr Andrei Petrov, director general of Rosenergoatom, Rosatom operator subsidiary, said an acceptance certificate for the unit would now be issued by the regulatory authorities with a view to the granting of an operating licence in July.

Rosatom said that at the same time, onshore and hydraulic structures for the plant, as well as infrastructure ensuring the transmission of electricity to the local grid and heating for the city’s network, are scheduled to be completed by the end of this year in Pevek, which is the Chukotka region of northern Russia. Engineering work is running to schedule.

The plant is scheduled to be towed to the Port of Pevek during the summer shipping season where it will replacing the outgoing capacities of the Bilibino nuclear power plant and the Chaunskaya combined heat and power plant. It is expected to be connected to the power grid in December.

Source : World Nuclear News
Bijlage:
voda
0
Japan to suspend operations at nuclear plants if deadline missed

Xinhua reported that Japan's nuclear watchdog denied requests from power companies to extend deadlines for them to complete steps to install measures to protect against terrorism at their nuclear facilities. The Nuclear Regulation Authority said it would suspend the operations at plants that have not fulfilled anti-terrorism measures instituted in 2013 under stricter operational guidelines after the 2011 Fukushima nuclear crisis. Under the guidelines, the operators of nuclear power plants are required to build facilities to safeguard against terrorist attacks, such as standby control rooms so that reactors can still be controlled remotely even in the event of a plane being flown into a plant.

This is in order to prevent the recurrence of the massive amounts of radioactive material that was released into the air, ground and sea following Tokyo Electric Power Co losing control of key cooling and backup functions at the Fukushima Daichi nuclear facility, leading to core meltdowns in reactors after the plant was hit by an earthquake-triggered tsunami.

The ongoing crisis at the plant remains the worst nuclear crisis in the world since the 1986 Chernobyl disaster.

The operators, under the new post-Fukushima guidelines, were given within five years to make the counter terrorism upgrades after their reactors cleared safety inspections and were brought back online.

But three power companies, Kyushu Electric, Kansai Electric and Shikoku Electric, said they need more time to implement the anti-terrorism changes at the five plants they collectively operate in western and southwestern Japan.

Seven reactors at four of the plants have already cleared the preliminary safety inspections and have been brought back online.

The power companies have said, however, that they will need between one and two-and-a-half years to complete the required upgrades, with the No. 1 reactor of the Sendai power plant in Kagoshima Prefecture facing the earliest suspension if the necessary work is not completed by March 2020.

The NRA has said it will listen to the operators' opinions and evaluate alternative measures the utilities have or will be implementing in terms of defending against possible acts of terrorism.

Source : Xinhua
voda
0
CGN agrees to invest in completion of Romanian reactors

A preliminary investors' agreement has been signed between Romanian national nuclear company Nuclearelectrica and China General Nuclear regarding the completion of units 3 and 4 at the Cernavoda nuclear power plant. The unfinished units 3 and 4 at Cernavoda (Image: Nuclearelectrica)
The investors' agreement in the preliminary form was signed at the Ministry of Energy in Bucharest by Nuclearelectrica, CGN and CGN Central and Eastern Europe Investment (Romania) Co. The signing took place in the presence of Romanian Vice Prime-Minister Viorel Stefan; Minister of Energy Anton Anton; China's Ambassador Extraordinary and Plenipotentiary to Romania Jiang Yu; and Economic Counsellor of China to Romania Guan Gang.

The PIA was approved by Nuclearelectrica's shareholders during its General Meeting of Shareholders on 10 April. CGN has also completed its internal approval process of the agreement.

The agreement calls for the setting up of a joint venture project company as a "technical and operational platform" for the completion of Cernavoda 3 and 4, which will be 700 MWe Candu 6 pressurised heavy water reactors. Under the agreement, the joint venture will be established within the next 60 working days for an initial period of two years. CGN will hold a 51% stake in the project company, with Nuclearelectrica holding the remaining 49%.

Mr Anton said that "Reaching a consensus in the negotiation process, mutually advantageous for both parties, realised by the approval of Nuclearelectrica's shareholders of the investors' agreement in the preliminary form, is in actuality the effective initiation of the concrete measures to continue and develop of Cernavoda units 3 and 4. During the initial two-year duration of the new project company we will define and structure the model to continue the project, being in fact the first essential stage prior to the construction of the two units."

Mr Bian Shuming, general manager of CGN Romania Nuclear Power Co said that CGN is fully committed to working closely together with its Romanian partner on the successful development of the next phases of the project in line with the agreed principles.

Cernavoda is already home to two operating Candu 6 reactors supplied by Candu Energy's predecessor, Atomic Energy of Canada Ltd (AECL), and built by a Canadian-Italian consortium of AECL and Ansaldo. Unit 1 started up in 1996, but work was suspended on a further four units in 1991. Unit 2 was subsequently completed and has been in operation since 2007.

Source : Strategic Research Institute
Bijlage:
voda
0
Two units of Kudankulam Nuclear Power perform below par

The two units of Kudankulam Nuclear Power Project have generated far less power in the last financial year compared to the previous year. The Unit 1 has generated 36% less power in 2018-19 and Unit 2 has generated 22% less than the previous year as per the data available on NPCIL website. This is the first time both the units have together reported drop in power generation.

The Unit 1 has not generated power in the entire month of March and Tangedco sources said at any given time last year, only one unit was functioning. Set up at a huge cost, the units have been hit by various problems and NPCIL is not coming out in the open about the issues.

A senior NPCIL official said that “We had to take up maintenance issues in both the units and therefore the total power generated last year was less compared to the previous year. Both the units will restart in a few months." But he refused to detail the issues confronting the two units.

Tangedco gets more than 1000MW from the two units. A senior Tangedco official said that “The discom is dependant fully on private sector power companies or is purchasing from open market to make up for the loss from the nuclear power plants."

The official said that “Unfortunately, the NPCIL is not saying when the units will restart operation."

It has come to a stage where Tangedco has clubbed the Kudankulam power source along with renewable sources owing to the uncertainty in generation. “We are not able to prepare any schedule based on Kudankulam supply. It is as good as not being there,” said the official.

Since 2015-16, Unit 1 has generated 17,795 million units and since 2016-17, Unit 2 has generated 7,639 million units.

Source : Economic Times
Bijlage:
voda
0
Duke Energy To Decommission Retired Florida Nuclear Plant By 2027

Duke Energy announced a plan to decommission its previously retired Crystal River Nuclear Plant in Florida by 2027 nearly 50 years sooner than originally scheduled. The plan has no impact on customer bills. Duke Energy’s accelerated decommissioning plan is subject to approval by the US Nuclear Regulatory Commission and the Florida Public Service Commission. The process will take about a year to complete. If approved, decommissioning work will begin in 2020 and end in 2027.

Duke Energy previously announced its decision to retire the plant on Feb. 5, 2013, and to decommission it by 2074.

Decommissioning a nuclear plant is highly regulated and involves removing, packaging and shipping radioactive materials, such as the reactor vessel, to a licensed facility and then demolishing buildings.

To perform the work, Duke Energy has contracted with Accelerated Decommissioning Partners, a joint venture between NorthStar Group Services and Orano USA.

Source : Strategic Research Institute
Bijlage:
voda
0
BHEL Expands Its Offerings In Nuclear Projects

Against stiff competition, BHEL has secured a prestigious order for the erection work of the upcoming 2x1000 MWe Turbine Generator island Units 3&4 at Kudankulam Nuclear Power Project in Tamil Nadu being set up with foreign cooperation (Russia). Valued at over INR 440 Crore, the order has been placed on BHEL by Nuclear Power Corporation of India Limited. Significantly, for the same project, BHEL has also emerged as the lowest bidder for erection of the Reactor side equipment. Earlier, BHEL has successfully executed the erection work of TG island for Units 1&2 at Kudankulam, showcasing its capability in efficiently erecting equipment designed and manufactured by other suppliers. BHEL is an established EPC leader for both thermal and nuclear power projects. 12 out of 18 operating Pressurized Heavy Water Reactors in the country are equipped with BHEL-supplied steam turbine generator sets, accounting for 74% of the installed capacity.

BHEL is also currently executing turbine generator packages for 4 units of 700 MWe, 2 units each at Kakrapar and Rawatbhata.

Source : Strategic Research Institute
voda
0
Russian VVER-TOI NPP Was Found To Comply With The Eur Requirements

European power generation companies agreed that the most advanced Russian project of the VVER-TOI NPP complies with the European Utility Requirement. The ceremony of handing of the corresponding certificate was held in St. Petersburg on June 13.
Atomenergoproekt JSC (a company of Rosatom engineering division) is the general designer of VVER-TOI, Hydropress Design Bureau is the developer of the reactor plant and Scientific and Research Centre “Kurchatov Institute” is the scientific coordinator. Rosenergoatom JSC is the project owner.

At the ceremony, Mr Guillaume Jacquard, the EUR President, EDF Deputy Director of the Directorate for Project Support and Digital Transformation, thanked all the participants for their hard work. He said that “I can state that the VVER-TOI Project has passed the most thorough and precise examination and it fully complies with the requirements of EUR.”

The conclusions on the compliance of design solutions with the EUR requirements were made by the European experts based on a review of the design documentation and information provided in the documents on the reference project of the Kursk NPP-2.

The analysis included review of the answers to 4,332 fundamental safety-related questions of the EUR requirements, which cover the entire complex of the nuclear power plant.

As a result, European experts concluded that the VEER-TOI design complies with modern views on safety and efficiency of the nuclear power plants. The analysis made it possible to improve the quality of subsequent projects and facilitate future operation of nuclear power plants.

Source : Strategic Research Institute
Bijlage:
voda
0
China Plans Small Nuke Reactors To Replace Coal And Gas Use

Reuters reported that China plans to build a pilot small-scale nuclear reactor that could replace coal or gas to heat towns and cities in its colder northern regions. Mr Wang Xujia, a senior engineer with the State Power Investment Corp said that the small heating reactor is planned for the city of Jiamusi in northeastern Heilongjiang province, one of two proposed units with a combined capacity of 400 megawatts.

Mr Wang on the sidelines of an industry conference told that “The project is still under central government review for approval adding that the developer aimed to put the project into operation by 2024.”

China has been exploring the use of small nuclear reactors – less than a fifth of the size of a standard reactor – as alternative heating systems in smog-prone northern regions. The state provides heating throughout northern China from November to March, using predominantly coal- or gas-fired boilers.

Source : Reuters
voda
0
China's Tops Out Hualong One Nuclear Plant In Pakistan

Global Construction Review reported that right on schedule, China National Nuclear Corporation this week successfully lifted the large outer containment dome into place at Karachi Unit 2 in Pakistan. It is the overseas debut of China’s homegrown third-generation HPR1000 reactor design, known as the Hualong One, which is currently being assessed for the new Bradwell B nuclear power station in Essex, UK.

In Karachi, ground broke in November 2012, and China lent USD 6.5 billion to Pakistan to help fund the USD 9.6 billion project.

State-owned CNNC said the milestone, achieved 17 June, marks the end of general construction on Karachi Unit 2, and will be followed by containment and heat tests.

The report said that the project is scheduled for completion next year. The HPR1000, China’s self-developed third-generation nuclear power technology, has a double containment design, with the outer containment providing secondary protection.

Source : Global Construction Review
Bijlage:
voda
0
Hinkley Point C Nuclear Power Plant Hits Its Biggest Milestone

Hinkley Point C has hit its biggest milestone yet on schedule. The completion of the base for the first reactor, known as “J-zero”, means that the construction of the nuclear buildings above ground can now begin in earnest. The final 9,000m³ of concrete was the largest concrete pour in the UK, beating a record set by the Shard in London. Reinforced with 5,000 tonnes of Welsh steel, the base has been under construction by the UK-French joint venture of Bouygues-Laing O’Rourke for six months.

Good progress and efficiency improvements means that the second Hinkley Point C reactor will hit its own J-zero moment in June 2020

Final contracts have now been signed for an innovative joint venture to install the pipes and cables at the power station. The MEH Joint Venture brings UK contractors Balfour Beatty, Cavendish Nuclear, Altrad and Doosan Babcock together to share expertise and incentivise collaboration and efficiency. The JV was influenced by the success of a single organisation carrying out this complex work during construction at Taishan, the EPR operating in China.

Pipework will be made by Bilfinger in Immingham at a modernised facility which will boost UK industrial capacity in this highly specialised area.

Source : Strategic Research Institute
Bijlage:
voda
0
TEPCO to Decommission Fukushima Daini Nuclear Plant

Tokyo Electric Power Company Holdings Inc will formally decide to decommission the Fukushima Daini nuclear plant after informing the prefecture's governor of its policy as early as this month. Excluding the nearby Daiichi, crippled by the March 2011 earthquake and tsunami disaster, it is the first time that the utility, also known as TEPCO, has decided to decommission a nuclear plant.

The decommissioning of all four nuclear reactors at Daini will likely require more than 40 years and some 280 billion yen ($2.6 billion) in costs, the source said. If realized, all 10 nuclear reactors in Fukushima Prefecture will be scrapped.

Closure of the Daiichi plant, which suffered core meltdowns at three of its six reactors, has already been decided.

After telling Fukushima Gov. Masao Uchibori about the policy, it may be formally approved at a TEPCO board meeting, scheduled at the end of this month, the source said.

The Daini complex was also hit by tsunami waves in the 2011 disaster and temporarily lost reactor cooling functions. But unlike the Daiichi plant, it escaped meltdowns.

Source : Japan Today
voda
0
Start up of Olkiluoto 3 Delayed by Six More Months Until July 2020

TEOLLISUUDEN VOIMA has revealed it has received an updated schedule for the start-up of Olkiluoto 3, the third plant unit at Olkiluoto Nuclear Power Plant in Eurajoki, Finland, from Areva-Siemens. According to the new schedule, the unit is currently expected to commence regular electricity production six months behind the previous schedule, in July 2020.

Areva-Siemens, the French-German consortium supplying the unit, announced this spring it will update the start-up schedule on grounds that modification outage work carried out at the site was progressing slower than expected.

The plant supplier has now stated that nuclear fuel will be loaded into the reactor in January 2020, that the unit will be connected to the national grid in April 2020, and that the unit will start regular electricity production in July 2020. The commissioning programme indicates that the unit will produce one to three terawatt hours of electricity with varying power levels during the period between first connection to grid and start of regular electricity production.

Mr Jouni Silvennoinen, the project manager at TVO said that “The re-baseline is now more exhaustive, which we believe will make it possible to improve project performance. The scheduling work was not only a schedule updating exercise, but it consisted of methodology to change the ways of working.”

He added that “Although, the completion of the plant unit will be further delayed, we are currently working to reach the fuel loading phase and to take over the OL3 EPR [a third-generation pressurised water generation] unit.”

Source : Strategic Research Institute
Bijlage:
847 Posts, Pagina: « 1 2 3 4 5 6 ... 19 20 21 22 23 24 25 26 27 28 29 ... 39 40 41 42 43 » | Laatste
Aantal posts per pagina:  20 50 100 | Omhoog ↑

Meedoen aan de discussie?

Word nu gratis lid of log in met uw e-mailadres en wachtwoord.

Direct naar Forum

Markt vandaag

AEX 874,02 -0,77 -0,09% 24 apr
AMX 925,76 -8,67 -0,93% 24 apr
ASCX 1.207,07 +3,02 +0,25% 24 apr
BEL 20 3.883,83 -6,88 -0,18% 24 apr
Germany40^ 18.086,70 -2,00 -0,01% 24 apr
US30^ 38.353,31 0,00 0,00% 24 apr
US500^ 5.072,39 0,00 0,00% 24 apr
Nasd100^ 17.524,13 0,00 0,00% 24 apr
Japan225^ 37.998,76 0,00 0,00% 24 apr
WTI 82,90 0,00 0,00% 24 apr
Brent 88,08 0,00 0,00% 24 apr
EUR/USD 1,0705 +0,0008 +0,07% 05:53
BTC/USD 64.558,77 -1.813,21 -2,73% 02:59
Gold spot 2.313,52 -2,60 -0,11% 05:53
#/^ Index indications calculated real time, zie disclaimer
HOGE RENDEMENTEN OP DE IEX-MODELPORTEFEUILLES > WORD NU ABONNEE EN PROFITEER VAN MAAR LIEFST 67% KORTING!

Stijgers & Dalers

Stijgers Laatst +/- % tijd
ASMI 590,000 +58,400 +10,99% 24 apr
BESI 139,000 +5,450 +4,08% 24 apr
RANDSTAD NV 46,470 +1,470 +3,27% 24 apr
Dalers Laatst +/- % tijd
ING 14,670 -0,930 -5,96% 24 apr
RELX 38,500 -0,800 -2,04% 24 apr
DSM FIRMENICH AG 104,000 -2,150 -2,03% 24 apr

EU stocks, real time, by Cboe Europe Ltd.; Other, Euronext & US stocks by NYSE & Cboe BZX Exchange, 15 min. delayed
#/^ Index indications calculated real time, zie disclaimer, streaming powered by: Infront