BAM Groep « Terug naar discussie overzicht

BAM september 2019

2.798 Posts, Pagina: « 1 2 3 4 5 6 ... 123 124 125 126 127 128 129 130 131 132 133 ... 136 137 138 139 140 » | Laatste
boldie
0
quote:

master64nl schreef op 26 september 2019 23:46:

Zal het een Hagemeyertje worden?
liever vandaag dan morgen:)
boldie
0
OnoMatopee
0
quote:

boldie schreef op 27 september 2019 08:14:

[...]link werkt niet
https://www.ka-news.de/region/karlsruhe/ksc-stadion./KSC-versus-Stadt-Karlsruhe-Wie-geht-der-Streit-ums-Stadion-aus-Die-Urteilsverkuendung-im-Live-Ticker;art6066,2435696
OnoMatopee
0
RRS David Attenborough: Bam reveals Antarctic build challenge

27 Sep, 2019 By Miles Rowland

Members of the Bam Nuttall team who built the wharf to accommodate the new Antarctic research ship RRS Sir David Attenborough with Ramboll, have revealed the challenges of working in the uncompromising environment.

Some 60 Bam Nuttall workers were in the South Pole on phase 1 of the project for the British Antarctic Survey (BAS) between November 2018 and April 2019.

Speaking to Construction News at an event ahead of the official naming of the boat, Bam Nuttall operations director Graham Hopper revealed his team worked from 7am-7pm, six days per week, to make the most of the time they had.

Those selected for the project were required to undergo psychological evaluations to make sure that they would be prepared for the lengthy and isolated stint on the project, working in temperatures which regularly dropped to -10 deg C.

But Mr Hopper said that many of the workers were keen to go back. “To be honest, an Antarctic summer is probably a far better place to be in the Scottish winter. It’s cold but a dry cold," he said.

Some 4,500 tonnes of equipment and parts of the steel frame of the wharf were transported to Antarctica by ship. The steel frame had been constructed offsite in the UK using modular techniques and was ‘flat-packed’ during transit to maximise the usage of space. Mr Hopper said it took a month and cost £2m to transport all that was necessary for the project.

Tailored contingency plans are also needed for such a remote project. “You’re going to Antarctica, you need contingency. Whereas your construction methodology requires a 300 tonne crane and say a 150 tonne crane, you have to take two 300 tonne cranes, because if your large crane breaks down, your 150 tonne model won’t be able to support that," he said.

Diggers used on the project needed to be fitted with long-reach attachments due to the requirements of the terrain, which operatives were trained to use via an Xbox simulation before they left the UK.



The wharf and research vessel are part of a £200m UK government investment into polar science.

Construction is due for completion in April 2020.
OnoMatopee
0
om de verveling te verdrijven nog maar een keertje

BAM scoops £350m Leeds Temple district phase 1
Aaron Morby 55 mins ago
Share

Developer CEG has named BAM Construction as preferred contractor for the first phase of its £350m new Temple district scheme in Leeds.

The South Bank regeneration development at Globe Road will include a 38,000 sq ft office building with ground floor retail and leisure space.

Following further detailed design work, BAM will start building the Globe Point project in early 2020.

The second phase, which also has detailed planning permission, could come forwards simultaneously and agents Fox Lloyd Jones and Knight Frank are identifying occupiers now.

This building would offer 138,168 sq ft with ground floor retail and leisure.

Globe Point is based in a new district within the city centre – Temple – forming a key part of the South Bank Regeneration Area of Leeds, adjacent to Leeds trains station.

CEG also has outline planning permission for further development of up to 1.1m sq ft of offices, shops, cafes, restaurants, bars, hotel and up to 750 new homes.

Architects Feilden Clegg Bradley Studios is working with CEG to masterplan Temple.

John Phillips, Director of BAM Construction in the North East, said: ‘This is an imaginative and bold scheme and any contractor would be excited to be involved with it.”
boldie
0
quote:

TomTom12 schreef op 27 september 2019 08:39:

PO op 2,30 maar zal wel weer wegzakken om 8:59:59
neehoor knallen gelijk door naar de 2.35 vlam in de pan:) damn wat is die koffie sterk vandaag:)
HenkdeV
0
quote:

TomTom12 schreef op 27 september 2019 08:39:

PO op 2,30 maar zal wel weer wegzakken om 8:59:59
De beurs opent praktisch onveranderd en het is ook nog vrijdag. Stel je er maar niet te veel van voor.
RIZ
0
quote:

OnoMatopee schreef op 27 september 2019 08:36:

om de verveling te verdrijven nog maar een keertje

BAM scoops £350m Leeds Temple district phase 1
Aaron Morby 55 mins ago
Share

Developer CEG has named BAM Construction as preferred contractor for the first phase of its £350m new Temple district scheme in Leeds.

The South Bank regeneration development at Globe Road will include a 38,000 sq ft office building with ground floor retail and leisure space.

Following further detailed design work, BAM will start building the Globe Point project in early 2020.

The second phase, which also has detailed planning permission, could come forwards simultaneously and agents Fox Lloyd Jones and Knight Frank are identifying occupiers now.

This building would offer 138,168 sq ft with ground floor retail and leisure.

Globe Point is based in a new district within the city centre – Temple – forming a key part of the South Bank Regeneration Area of Leeds, adjacent to Leeds trains station.

CEG also has outline planning permission for further development of up to 1.1m sq ft of offices, shops, cafes, restaurants, bars, hotel and up to 750 new homes.

Architects Feilden Clegg Bradley Studios is working with CEG to masterplan Temple.

John Phillips, Director of BAM Construction in the North East, said: ‘This is an imaginative and bold scheme and any contractor would be excited to be involved with it.”
BAM dit al gemeld?
boldie
0
quote:

HenkdeV schreef op 27 september 2019 08:46:

[...]

De beurs opent praktisch onveranderd en het is ook nog vrijdag. Stel je er maar niet te veel van voor.
misschien dat ze vroeg aan de vrijdagmiddag borrel beginnen...
innicksname
0
quote:

boldie schreef op 27 september 2019 08:45:

[...]neehoor knallen gelijk door naar de 2.35 vlam in de pan:) damn wat is die koffie sterk vandaag:)
Niks mis mee, als je hem maar niet té warm drinkt.
boldie
0
quote:

OnoMatopee schreef op 27 september 2019 09:12:

151k dump
buiten boekje om dan neem ik aan
2.798 Posts, Pagina: « 1 2 3 4 5 6 ... 123 124 125 126 127 128 129 130 131 132 133 ... 136 137 138 139 140 » | Laatste
Aantal posts per pagina:  20 50 100 | Omhoog ↑

Meedoen aan de discussie?

Word nu gratis lid of log in met uw e-mailadres en wachtwoord.

Direct naar Forum

Detail

Vertraagd 10 mei 2024 17:35
Koers 3,492
Verschil +0,034 (+0,98%)
Hoog 3,516
Laag 3,454
Volume 909.065
Volume gemiddeld 1.577.049
Volume gisteren 539.255

EU stocks, real time, by Cboe Europe Ltd.; Other, Euronext & US stocks by NYSE & Cboe BZX Exchange, 15 min. delayed
#/^ Index indications calculated real time, zie disclaimer, streaming powered by: Infront